BRAC / FAIRFAX COUNTY PARKWAY EXTENSION PROJECTDaytime work - Closures occur between 9 a.m. to 5 p.m. unless otherwise noted.
- Fairfax County Pkwy. (Route 7100) south from Sydenstricker Rd. to Gambril Rd. - Single lane closed Monday - Friday for barrier work and overhead sign installation.
- Franconia Springfield Pkwy. (Route 7900) east from the Whitler's Creek Dr. to Accotink Creek bridge - Single lane closed Monday - Friday for median construction and new exit ramp work.
- Fairfax County Pkwy. (Route 7100) north and south from Barta Rd. to Franconia Springfield Pkwy. (Route 7900) - Single lane closed Monday - Friday for construction in median work.
- Hooes Rd. east and west at Barkers Ct. - Flagger operation Monday - Friday for construction entrance work.
Ongoing work Fairfax County Parkway Extension Project
- The Fairfax County Parkway extension (Route 7100) is now open. For more information and detour maps click here.
Read more about the Fairfax County Parkway.
DULLES CORRIDOR METRORAIL PROJECT
Nighttime work - Closures occur between 9:30 p.m. and 5 a.m. unless otherwise noted.
- I-495 north to Exit 46A, Chain Bridge Rd. (Route 123) south - Ramp closed Sunday - Friday nights for bridge work. Traffic will be directed to take Exit 46B, Chain Bridge Rd. (Route 123) north, make a right on Old Meadow Rd., left on Colshire Dr. and then follow signs to Chain Bridge Rd. (Route 123) south.
- Leesburg Pike (Route 7) west at Westwood Center Dr. - Left turn lane closed Sunday - Wednesday nights for bridge work. Traffic will be directed to follow posted detour signs.
- Leesburg Pike (Route 7) east at Tyco Rd. - Left turn lane closed Sunday - Wednesday nights for bridge work.
- Leesburg Pike (Route 7) east from Spring Hill Rd. to Gosnell Rd.- Two right lanes closed Thursday and Friday nights for roadway work.
- Chain Bridge Rd. (Route 123) north and south at Tysons Blvd. - Left turn lane closed Monday - Friday nights for bridge work. Traffic will be directed to follow posted detour signs.
- Chain Bridge Rd. (Route 123) south to I-495 north - Ramp closed Sunday - Friday nights for bridge work. Traffic will be directed to continue south, make a right onto International Dr. north, make a right onto Galleria Dr. east, right onto Tysons Blvd., left onto Chain Bridge Rd. (Route 123) north and follow signs to I-495 north.
- Westwood Center Dr. east at Leesburg Pike (Route 7) - Left turn lane and through lane closed Sunday - Wednesday nights for bridge work. Traffic will be directed to follow posted detour signs.
- Tyco Rd. west at Leesburg Pike (Route 7) - Left turn lane and through lane closed Sunday - Wednesday nights for bridge work. Traffic will be directed to follow posted detour signs.
- Westpark Dr. east and west at Leesburg Pike (Route 7) - Left turn lanes and through lanes closed Monday and Tuesday nights for crane work. Traffic will be directed to follow posted detour signs.
- Galleria Dr. east at Tysons Blvd. - Right turn lane closed Monday - Friday nights for bridge work. Traffic will be directed to follow posted detour signs.
- Tysons Blvd. east at Galleria Dr. - Right turn lane closed Monday - Friday nights for bridge work. Traffic will be directed to follow posted detour signs.
- Dolley Madison Blvd. (Route 123) south from Capital One Dr. to I-495 - Right lane closed Sunday - Friday nights for bridge work.
- Old Ox Rd. (Route 606) east or west at Murcer Cir. - Road closed Tuesday and Wednesday night for ground maintenance.
Police will be on site for motorist safety. All closures are weather permitting.
Weekday work - Closures occur between 9:30 a.m. and 3:30 p.m. unless otherwise noted.
- Expect daytime delays in the Tysons Corner area along the Dulles Connector Road (Route 267), Leesburg Pike (Route 7) and Dolley Madison Blvd. (Route 123).
All closures are weather permitting.
Read more about the Dulles Metrorail Project.
495 EXPRESS LANES PROJECT
Nighttime work - Closures occur between 9:30 p.m. and 5 a.m. unless otherwise noted.
- I-495 south from Old Dominion overpass to Exit 46, Chain Bridge Rd. (Route 123) - Three lanes closed Sunday - Thursday nights for overhead sign work. Expect intermittent full road closures of up to 30 minutes after midnight.
- I-495 north or south from Lewinsville Rd. overpass to Old Dominion Dr. overpass - Three lanes closed Friday and Saturday nights for survey work. Expect intermittent full road closures of up to 30 minutes after midnight.
- Dulles Connector Rd. (Route 267) east to I-495 north- Ramp closed Sunday - Tuesday nights for bridge overhang work. Traffic will be directed to take I-495 south to Exit 46B, Chain Bridge Rd. (Route 123) north, stay to the right and follow signs to I-495 north.
- Chain Bridge Rd. (Route 123) south to I-495 north - Ramp closed Sunday night for overhead sign work. Traffic will be directed to continue south, follow signs to I-495 south, stay to the right entering back onto Chain Bridge Rd. (Route 123) north and follow signs to I-495 north.
- I-495 north from Exit 47, Leesburg Pike (Route 7) to Exit 45, Dulles Toll Rd. (Route 267) - Three right lanes closed Monday - Saturday nights for steel beam erection. Expect intermittent full road closures of up to 30 minutes after midnight.
- I-495 north to Exit 47A, Leesburg Pike (Route 7) west - Ramp closed Monday - Saturday nights for steel beam erection. Traffic will be directed to take Exit 47B, Leesburg Pike (Route 7) east and make a U-turn at George Marshall Dr. onto Leesburg Pike (Route 7) west.
- I-495 north to Exit 47B, Leesburg Pike (Route 7) east - Ramp closed Friday and Saturday nights for traffic shift. Traffic will be directed to continue north to Exit 46A, chain Bridge Rd. (Route 123) south, stay to the right, follow signs to I-495 south and take Exit 47A, Leesburg Pike (Route 7) west.
- Leesburg Pike (Route 7) east to I-495 north - Ramp closed Monday - Saturday nights for steel beam installation. Traffic will be directed to continue east, make a U-turn at George Marshall Dr. onto Leesburg Pike (Route 7) west and follow signs to I-495 north.
- Leesburg Pike (Route 7) east and west at I-495 - Multiple lanes closed Sunday - Tuesday nights for utility work.
- I-66 west to I-495 south - Ramp closed Sunday - Saturday nights for bridge work. Traffic will be directed to continue west to Exit 62, Nutley St. south, stay to the right, follow signs to I-66 east to I-495 south.
- I-66 west from Exit 67, Dulles Connector Rd. (Route 267) to Exit 64, I-495 - Two lanes closed Sunday - Saturday nights for utility work and traffic shift. Expect intermittent full road closures of up to 30 minutes after midnight.
- I-66 east from Exit 62, Nutley St. overpass to I-495 - Left lane closed Sunday - Saturday nights for bridge work.
- Nutley St. south to I-66 east - Ramp closed Sunday - Saturday nights for overhead sign installation. Prior to work zone, traffic will be directed to take I-66 west to Exit 57A, Lee Jackson Memorial Hwy. (Route 50) east, stay to the right and follow signs to I-66 east.
- Nutley St. north to I-66 east - Ramp closed Sunday - Saturday nights for overhead sign installation. Traffic will be directed to take I-66 west to Exit 57A, Lee Jackson Memorial Hwy. (Route 50) east, stay to the left and follow signs to I-66 east.
- I-495 north and south at Exit 51, Gallows Rd. (Route 650) - Three left lanes closed Friday and Saturday nights for overhang work. Expect intermittent full road closures of up to 30 minutes after midnight.
- Gallows Rd. (Route 650) north to I-495 south - Ramp closed intermittently for up to 30 minutes after midnight Friday and Saturday nights for overhang work.
- I-495 south to Exit 54B, Braddock Rd. (Route 620) west - Ramp closed Sunday - Friday nights for restriping. Traffic will be directed to take Exit 54A, Braddock Rd. (Route 620) east, stay to the right, follow signs to I-495 north, stay to the right to enter back onto Braddock Rd. (Route 620) west.
- I-495 north/west (Inner Loop) at Exit 174, Van Dorn St. - Left lane closed Wednesday and Thursday nights for overhead sign work.
Police will be on site for motorist safety.
All closures are weather permitting.
Weekday work- Closures occur between 9:30 a.m. and 3:30 p.m. unless otherwise noted.
- I-66 east general purpose (right exit) to I-495 north - Left lane of exit ramp will close Monday - Friday for drainage work.
OR - I-66 east HOV (left exit) to I-495 - Ramp closed Monday - Friday for road work. Traffic will be directed to use the I-66 east general purpose (right exits) to either I-495 north or south.
Expect single lane closures on the Inner and Outer Loops of I-495 from Springfield Interchange to beyond the Dulles Toll Rd. (Route 267) within the project area including all connecting arterials.
Ongoing work
- Twelve interchanges along the I-495 corridor from the Springfield Interchange to just north of the Dulles Toll Road are under construction until December 2012. Visit the 495 Express Lanes Interchange Fact Sheet Page.
Read more about the 495 Express Lanes Project.
BRAC/ FORT BELVOIR INTERSECTION IMPROVEMENTS AT ROUTE 1
Daytime work - Closures occur between 9 a.m. to 5 p.m. unless otherwise noted.
- Richmond Hwy (Route 1) north and south at Belvoir Rd. - Single lane closed Monday - Saturday for signal work and road widening.
- Richmond Hwy (Route 1) north and south at Pohick Rd. - Single lane closed Monday - Saturday for ground and signal work.